Issue Of Provisional Completion Certificate And Entitled To Maximum Bonus Of Rs. 3,56,40,000/- In Lieu Of Earlier Completion (60 Days Prior) For The Project 'Rehabilitation And Up Gradation Of NH-18 (New NH-40) From Km 108/850 To Km 160/200 (Rayachoty To Kadapa Section) To Two Lane With Paved Should

  • 12 Feb 2019

We are pleased to inform you that, the project 'Rehabilitation and Up gradation of NH-18 (New NH-40) from Km 108/850 to Km 160/200 (Rayachoty to Kadapa section) to two lane with paved shoulder in the state of Andhra Pradesh under corridor approach through Engineering, Procurement & Construction (EPC) basis' has been provisionally completed. The Provisional Completion Certificate has been issued by the authority on February 11, 2019 and has declared the project fit for entry into commercial operation as on September 10, 2018 and consequently the Company is entitled to maximum bonus of Rs. 3,56,40,000/- in lieu of earlier completion (60 days prior to the schedule completion date) of the said Project.

The trading window for dealing in the securities of the Company by its designated employees, specified persons, Immediate relatives and connected person shall be closed from February 12, 2019 to February 14, 2019 (both day inclusive).